Drummoyne Apartments Progress
The Drummoyne apartments are progressing on track for completion in late 2018. We have recently finished pouring the two underground carpark levels and the slab at ground level – the biggest slab of the project. We are looking forward to completing the upper two floors in the new year. The project includes post-tensioned slabs to achieve maximum spans with minimal supports.